The two Wichita State University Mixed Use Retail buildings are under construction near the intersection of 21st Street and North Oliver in Wichita KS.

Needham DBS designed the project as a design/build fast track project for Crossland Construction. Needham DBS was awarded the steel package on July 27, 2017 as the design drawings were nearing completion. Anchor Bolts were on site August 7, Joist and Deck were delivered to the site on September 8 and the remainder of the primary steel arrived September 18, 2017. Sunshades were delayed about a month but allowed the primary steel erection to be completed and stud work started before the sunshades were installed.

There’s a lot of activity on the east side of the WSU campus and we are thrilled to be part of this new development.